| Â Construction Activity | Programme |
| Pre-construction Site Works; Vegetation clearance, ecological mitigation, UXO surveys etc. |
February - April 2012 |
| Site Establishment | April - May 2012 |
| Construction; | May - June 2012 |
| Embankments | May - October 2012 |
| Habitat creation; Small ditches, ponds, wetland scrapes, tern islands |
May - October 2012 |
| New car park | June - September 2012 |
| Remove existing car park | August 2012 |
| Landscaping | August - October 2012 |
| Porter’s Sluice pumping station | May - October 2012 |
| Breach | April - June 2013 |
| Site Demobilisation | May - June 2013 |